Grid connection consultants for wind

Most onshore wind capacity in the UK is in Scotland, where the transmission network starts at 132 kV. That means relatively small distribution-connected wind projects in Scotland can still need assessment for their impact on the transmission system.

Jump to the 19 ranked consultancies

Typical size
5 MW to 300 MW+ onshore
Typical voltage
33 kV to 275 kV
Route
DNO or transmission, often with transmission impact assessment in Scotland
Timeline
Dependent on Gate 2 outcome and local transmission reinforcement
§01Context

Connecting wind in the UK

Consultancies in this category cover transmission applications through NESO, distribution applications, power systems studies and offer review.

Current regulatory issues

  • Repowering existing sites can make use of existing connection capacity, subject to agreement.
  • Transmission reinforcement programmes in Scotland affect connection dates for many projects.
§02Ranking

Track record counts only projects in this sector.

Best grid connection consultants for wind

Ranked by a published formulaMethodology

Grid connection consultants for wind
RankConsultancyServicesDNO coverageTypical sizeScore
01Green Cat Renewables

Biggar · est. 2005 · 51-200 staff

Unverified

Wind · Solar · BESS

ServicesDNO areas05/15Size500 kW – 69 MWScore54.4
02Power On Connections

Coventry · est. 2003 · 200+ staff

Unverified

Data centre · Industrial · Housing · BESS · Solar · Wind

ServicesDNO areas14/15Size500 kW – 100 MWScore35.9
03Grid Connection Consulting

Linlithgow · est. 2007 · 1-5 staff

Unverified

Wind · Solar · BESS

ServicesDNO areas00/15Size150 kW – 2000 MWScore33.6
04Power and Grid Engineering

Stoke-on-Trent · est. 2022 · 1-5 staff

Unverified

Solar · Wind · BESS · Data centre · Industrial

ServicesDNO areas14/15Size1–100 MWScore31.6
05SLR Consulting

London · est. 1994 · 200+ staff

Unverified

Wind · Solar · BESS · Data centre · Industrial · EV hubs

ServicesDNO areas01/15Size1–100 MWScore30.9
06Aurora Power Consulting

Bristol · est. 2007 · 6-15 staff

Unverified

BESS · Solar · Wind · Data centre · Industrial

ServicesDNO areas00/15Size10–250 MWScore30.4
07Blake Clough Consulting

Slaithwaite · est. 2021 · 51-200 staff

Unverified

Wind · Solar · BESS · Data centre

ServicesDNO areas00/15Size50–110 MWScore28.9
08TNEI

Manchester · est. 1999 · 51-200 staff

Unverified

Wind · Solar · BESS · Data centre · Industrial

ServicesDNO areas00/15Size1–200 MWScore24.5
09Engineering Power Solutions

Stockton-on-Tees · est. 2012 · 6-15 staff

Unverified

BESS · Wind · Solar · Data centre · Industrial

ServicesDNO areas01/15Size2–200 MWScore24.2
10Natural Power

Castle Douglas · est. 1995 · 200+ staff

Unverified

Wind · Solar · BESS

ServicesDNO areas00/15Size5–100 MWScore22.7
11RSK Utility Consulting

Ipswich · est. 2018 · 6-15 staff

Unverified

Wind · BESS · Solar · EV hubs · Housing · Industrial · Data centre

ServicesDNO areas02/15Size50 kW – 100 MWScore22.6
12Pure Green Consulting

Newport · est. 2017 · 6-15 staff

Unverified

Solar · BESS · Wind

ServicesDNO areas01/15Size25–600 MWScore21.7
13Action Renewables

Belfast · est. 2003 · 1-5 staff

Unverified

Wind · Solar

ServicesDNO areas01/15Size50 kW – 10 MWScore18.6
14ADTEK

Newcastle upon Tyne · est. 2012 · 1-5 staff

Unverified

Wind · Solar · BESS

ServicesDNO areas00/15Size1–50 MWScore17.9
15Decerna

Cramlington · est. 2012 · 6-15 staff

Unverified

Wind · Solar · BESS

ServicesDNO areas01/15Size3–250 MWScore17.4
16Locogen

Edinburgh · est. 2009 · 16-50 staff

Unverified

Wind · Solar · BESS

ServicesDNO areas00/15Size20–110 MWScore15.8
17Roadnight Taylor

Burford · est. 2013 · 16-50 staff

Unverified

Data centre · BESS · Solar · Wind · Industrial · Housing

ServicesDNO areas00/15Size1–100 MWScore15.6
18PSE2 Consulting

Bristol · est. 2016 · 6-15 staff

Unverified

EV hubs · Solar · Wind · BESS · Industrial

ServicesDNO areas01/15Size1–50 MWScore15.4
19Artios Energy

Edinburgh · est. 2021 · 1-5 staff

Unverified

Wind · Solar · BESS

ServicesDNO areas00/15Size1–100 MWScore15.2

See the full UK rankingGet matched with consultants for wind

§03Questions

Wind: common questions

Q01Why do small Scottish wind farms need transmission assessments?

In Scotland the transmission network includes 132 kV, so the distribution network is closer to the transmission boundary. Embedded projects can therefore affect the transmission system and may need assessment before connection.

Q02Does repowering a wind farm need a new grid connection?

Not always. If the repowered site stays within its existing capacity and technical parameters, the existing agreement may be modified rather than replaced. Increases in capacity usually need a new application.

Q03Who applies for a transmission connection?

In Great Britain, applications for transmission connections are made to NESO, which coordinates with the relevant transmission owner.